Visund Nord IOR


All posts for Visund Nord IOR

NPD: Fast IOR pProject on Visund

Operator Equinor has started production on Visund Nord in the North Sea. The project was completed in 21 months. The subsea solution adds 2.1 million standard cubic metres (13.3 million barrels) to the Visund field. The development cost was NOK 1.3 billion. Production licence 120 Visund was p ...

OilVoice Press - OilVoice


Posted 1 year agoPress > NPDNorwayNorwegian Petroleum Directorate +5

Equinor: Record Fast-Track Development

Manifold ready for installation at Visund Nord IOR. On 2 September the Visund Nord IOR (improved oil recovery) project came on stream, two months ahead of schedule. The project has further been delivered with no serious HSE incidents and well below budget. “It took 21 months from t ...