Operational update from Genel Energy

Posted by OilVoice Press

23-Dec-2016


Genel Energy plc ('Genel' or 'the Company') issues the following update in respect of the Taq Taq field (Genel 44% working interest).

The third and final well of the 2016 Taq Taq drilling programme, TT-16y, has been successfully drilled and completed in the main Shiranish reservoir. The well is naturally flowing at c.8,000 bopd. 

Gross Taq Taq production is currently c.40,000 bopd, with Q4 2016 averaging 45,000 bopd to date. The Pilaspi reservoir is being readied for production in January 2017, and is expected to contribute c.3,000 bopd. 

The three Shiranish wells (TT-27x, TT-07z, and TT-16y) drilled in the 2016 campaign are currently producing a combined c.9,000 bopd. Discussions are ongoing between the Taq Taq partners over a potential workover of TT-07z. This well flowed on test at 5,000-9,000 bopd, although as a result of mechanical issues experienced during well completion activities TT-07z has recently been producing at 400 bopd. 

Genel's net working interest production from the Taq Taq and Tawke fields has averaged 53,500 bopd in 2016 to date.  

The updated Field Development Plan and the Competent Person's Report for Taq Taq are on track for completion in Q1 2017. 

Genel plans to issue a trading and operations update in respect of 2016 financial and operating performance and 2017 outlook on Tuesday 24 January 2017.

Genel EnergyOperations Update

More items from oilvoice


EnQuest - Kraken First Oil

  EnQuest confirms that first oil from the Kraken development was delivered on 23 June 2017.  During the initial ramp-up period, the 13 wells that have been drilled and completed to date, comprising 7 producers and 6 injectors, are being brought online in a phased manner, to maximise long term pr ...

OilVoice Press


Posted 16 hours agoPress > EnQuestKrakenSpud Watch

US Atlantic Coast refiners face new threat in Buckeye proposal to reverse pipeline: Fuel for Thought

Storm clouds are gathering once again over US Atlantic Coast refineries, but unlike a few years ago when it was high oil prices causing a problem, this time the threat is coming from the Midwest. Hemmed in by geography, Midwestern refiners are looking east as a logical place to sell their gasoline ...

OilVoice Press


Posted 16 hours agoOpinion > PlattsBuckeyepipeline

Nord Stream 2: with Europe already divided, the US adds a new layer of geopolitical complexity

When Gazprom officially launched plans to build the second Nord Stream gas pipeline system to Germany in June 2015, the accusations that Gazprom's main aim was to increase its dominance over European gas came thick and fast. When five European majors from five EU member states (Austria, France, ...

OilVoice Press


Posted 16 hours agoOpinion > PlattsNord Streameurope +2

88 Energy - Icewine#2 Operations Update

88 Energy Limited ("88 Energy", "the Company", "Operator") (ASX, AIM: 88E) is pleased to provide an update on Project Icewine, located onshore North Slope of Alaska. Highlights Stage 2 stimulation operations completed successfully Icewine#2 Operations Update  Both stages of the planned tw ...

OilVoice Press


Posted 6 days agoPress > 88 EnergyProject IcewineAIM +1

Cairn secures new licences in Mexico bid round

  Cairn is pleased to announce it has secured interests in two licences in the Mexico offshore bid round. The licences (one operated and one non-operated, covering ~1,100km2) are located in the Gulf of Mexico in the shallow water Sureste basin in water depths of 100-500metres and ~50km offshore:  ...

OilVoice Press


Posted 6 days agoPress > Cairn EnergyMexicoGulf Of Mexico
All posts from oilvoice