Stainless Steel Tube Welding Without Argon Welding

Usually stainless steel pressure tube welding, stainless steel tubings filled with argon-protected tungsten argon arc welding bottom welding is a common method used for welding stainless steel and some special steel tubes, because this method is time-consuming, labor-intensive, gas-intensive and some welding ports can not be charged at all. Argon protection; try to use the slag protection method, that is, using a welding wire or a flux-cored wire with a coating for tungsten argon arc welding; in the operation process, considering the protection of the slag inside the tube, the general guiding ideology is It is intended to flow the scum on the molten pool into the tube to protect the inner surface weld.

Stainless steel tube welding without argon

Preparation before welding

  • 1. Clean the oil, dirt, scale, water and oxides near the interface of the weldment (1Cr18Ni9Ti 89×6mm) to make it shine.
  • 2. welding consumables: TGF 308L for self-protecting stainless steel argon-free welding wire 2.5mm; or ER 308L stainless steel flux cored wire 2.2mm. Cover surface (filled) welding with A132 stainless steel electrode 3.2mm.
  • 3. The front welding protection gas is generally argon gas, the purity should be greater than 99.95%, and the flow rate is generally 10L/min.
  • 4. making the groove, single side 30 ° ~ 35 °, group positioning, the wrong side is less than 1mm; using the welding wire for point fixed welding, horizontal fixed all position welding, three positioning welding points are evenly distributed, 6 points The position is the starting solder joint. To ensure the strength of the positioning solder joint, the length of the positioning weld is about 10mm, and the height is about 1/2 of the wall thickness. After the slag is removed, the two ends of the welded seam are ground into a gentle slope to facilitate the joint flatness.
  • 5. welding machine: WS400, tungsten 2.5mm, nozzle 14mm, welding wire TGF308L 2.5, current (priming) 90 ~ 110A, flow 10L / min.

Bottom welding

  • 1. Guide the arc on the groove surface and immediately retreat to the starting point of the slope root (usually about 10mm before the 6 o'clock position). When it starts to melt, immediately fill the welding wire to fuse the welding wire with the base metal. It is seen that the molten metal and the molten slag flow uniformly into the tube through the groove to form a molten hole; the welding gun swings in a small zigzag shape, moves upward slightly, the welding wire does not leave the argon gas protection, and is attached to the blunt edge of the groove. , using the intermittent wire feeding method, one pull and one send, one drop and one drop to fill the molten pool.
  • 2. in the welding process, to maintain short-arc operation; the handle should be stable, the wire should be clean, pay attention to the distance between the wire and the tungsten, to prevent "tungsten", otherwise it should be polished and then re-welded.
  • 3. Controlling the size and shape of the melt holes is the key to double-sided forming of the bottom weld.
  • 4. During the bottom welding process, the welding wire should be uniformly melted, and a thin layer of slag is uniformly penetrated into the nozzle to protect the weld seam. This is the reason why the medicated welding wire is used.
  • 5. after welding, hammering, so that the welding slag fall off; can also be used to remove the welding slag in the tube by compressed air or water, so that the tube gets a beautiful golden yellow weld.

Cover welding

  • 1. The weldment is made of two layers of bottom welding and cover welding.
  • 2. the welding material of the cover welding is A132 stainless steel electrode, the size is 3.2mm, the current is 80~120A.
  • 3. the welding position is all-position welding, short arc welding should be adopted, and the overlap should be greater than 10mm.
  • 4. slow cooling after welding.

Test

Posted by stainless steel tubing supplier and stainless steel pipe supplier KAYSUNS.



New service from OilVoice
Trip Shepherd is for companies who need to track their staff in areas of risk.
It's free to use, so we invite you to try it.

Visit source site

https://kaysuns.com/stainless-steel-tube-welding-w...

stainless steel tubestainless steel tubingstainless steel pipe weldingKAYSUNSTube Weldingstainless steel pipe supplierstainless steel tubing supplier

More items from cnwellgreen


Advantages Of Duplex 2205 Pipe Over Oil Industry

Why Duplex Pipe Be Used In Oil Industry Compared with 316L and 317L stainless steels, 2205 duplex stainless steel has better performance in pitting and crevice corrosion resistance.It has high corrosion resistance and a lower coefficient of thermal expansion than austenite Higher thermal conductiv ...

roger chen - kaysuns industry limited


Posted 8 days agoPress > oil industryduplex pipeduplex 2205 pipe +1

Manufacturing Process of Duplex Pipe - Why Duplex Pipe is Expensive

Manufacturing Process of Duplex Pipe - Why Duplex Pipe is Expensive After more than ten years of development, the manufacturing process of duplex stainless steel pipes has gradually matured, it made the material from high-end to ordinary applications. Considering the relative cost, more and more c ...

roger chen - kaysuns industry limited


Posted 15 days agoPress > Manufacturing Processduplex pipeWhy Duplex Pipe is Expensive +1

IMO 2020 and Scrubber

In the coming 2020, the sulfur-limiting order formulated by the International Maritime Organization (IMO 2020) will bring a series of changes to shipping. According to the latest estimates by the Exhaust Gas Cleaning Systems Association (EGCSA), at least 4,000 ships will be equipped with scrubbers ...

roger chen - kaysuns industry limited


Posted 28 days agoPress > IMO 2020Exhaust Gas Cleaning Systems AssociationInternational Maritime Organization

Annual Output Value Reaches 10 Billion! Guangdong Yongjin's Stainless Steel Phase I Has Been Completed 90%, Trial Production Next Month!

We carry out the cold rolling process independently, all relying on the upstream raw material support. Here in Yangjiang city, we must rely on the supply of Guangqing's raw materials. Its raw material guarantee has great support for the supply of our customers. After the first phase of the project ...

roger chen - kaysuns industry limited


Posted 1 month agoPress > cold rolling processstainless steelYongjin inc. +1

Posco Achieves Steel Operating Profit Of More Than 1 Trillion Won For 9 Consecutive Quarters

Posco Achieves Steel Operating Profit Of More Than 1 Trillion Won For 9 Consecutive Quarters As of the end of the third quarter of 2019, POSCO has achieved operating profit of more than 1 trillion won for nine consecutive quarters. POSCO announced in a conference call on October 24 that in the thi ...

roger chen - kaysuns industry limited


Posted 1 month agoPress > POSCOKoreaSTEEL PROFITS
All posts from cnwellgreen