Equinor: Norway’s Largest Oil Pipeline Now in Place


Saipem Castorone at the Johan Sverdrup field
Saipem Castorone at the Johan Sverdrup field in the North Sea. (Photo: Bo B. Randulff / Roar Lindefjeld / Equinor ASA)

Last week Norway's largest and longest pipeline, laid by the vessel Saipem Castorone, reached the Johan Sverdrup field in the North Sea.

Late last week the last pipe of what is now Norway's longest and largest oil pipeline was installed right next to the riser platform at the Johan Sverdrup field. The 36-inch pipeline extends 283 km from the Mongstad oil terminal outside Bergen to the giant field in the North Sea. 

“We have together with our supplier Saipem succeeded in laying the oil pipeline to Johan Sverdrup without any serious incidents. It has been a significant operation, involving more than 600 people at the most, who have welded together over 23,000 pipes to create what has now become Norway's largest and longest oil pipeline,” says Geir Bjaanes, responsible for subsea, power and pipelines for the Johan Sverdrup project.

“The oil pipeline plays a really central role in the project. When the Johan Sverdrup field produces at peak, 660,000 barrels of oil valued at more than NOK 350 million each day, will flow daily into Mongstad,” says Bjaanes.

The vessel Saipem Castorone began pipelaying operations at Mongstad in late April this year. After, the pipeline was laid through the Fensfjord before the vessel set course for the Johan Sverdrup field. The operations have been executed with high quality and no serious incidents. 

With the oil pipeline installed Saipem Castorone is now getting ready for the next stage – laying the 156 km long gas pipeline that will extend from the Johan Sverdrup field to the Statpipe pipeline, from where gas from the field will eventually be shipped to Kårstø. The pipeline installation operations are expected to be completed during the autumn.

“We have spent many years with Saipem planning these operations. We're all very aware of the size of the task, with several months at sea with a significant installation scope. The key is to follow the thorough plans that we've prepared and maintain our significant focus on HSE along the way, until also the gas pipeline is in place,” says Tor Kåre Egelandsdal, responsible for the pipeline installation and the contract with Saipem.

When the pipeline operations are complete, the 2018 Johan Sverdrup installation campaign will be over. With three jackets, two topsides, one bridge, over 400 km of pipelines, and 200 km of power cables, the 2018 campaign is probably the busiest installation campaign ever for a project on the Norwegian continental shelf. And in 2019 the last two topsides and remaining bridges will be put in place before startup of the first phase of the Johan Sverdrup development expected in November next year.


Visit source site

https://equinor.com/en/news/10sep2018-norways-larg...

NorwayEquinorEquinor EnergypipelineNorth SeaNorwegian North SeaJohan SverdrupOffshore

More items from oilvoice


Africa E&P Summit

The organisers of the Africa E&P Summit are bringing together Africa's leading exploration companies and governments, just one of the many reasons why you should be attending frontier's event that they are organising and hosting in London at the IET: Savoy Place, 22-23 May. Over 200 key senior exec ...

OilVoice Press - OilVoice


Posted 13 days agoPress > Africasummitoil summit +2

Equinor Deepens in Offshore Wind in Poland

Equinor has exercised an option to acquire a 50 % interest in the offshore wind development project Bałtyk I in Poland from Polenergia. This transaction is a follow-up of the agreement between the two companies which came into force in May 2018 , by which Equinor acquired a 50 % inter ...

OilVoice Press - OilVoice


Posted 5 months agoPress > EquinorEquinor EnergyPoland +2

Nigeria has highest capex on crude and natural gas projects in sub-Saharan Africa Over Next Seven Years, says GlobalData

Nigeria accounts for more than 34% of the proposed capital expenditure (capex) on planned and announced crude and natural gas projects in the sub-Saharan Africa over the period 2018–2025, according to GlobalData , a leading data and analytics company. The company's report: ‘H2 2018 Production ...

OilVoice Press - OilVoice


Posted 5 months agoOpinion > GlobalDataNigeriaCrude +5

CNOOC Signs Strategic Cooperation Agreements with 9 International Oil Companies

HONG KONG, Dec. 18, 2018 /PRNewswire/ -- CNOOC Limited (the "Company", SEHK: 00883, NYSE: CEO, TSX: CNU) announced today that its parent company, China National Offshore Oil Corporation (CNOOC), has signed Strategic Cooperation Agreements with 9 international oil companies including: Chevron, Conoco ...

OilVoice Press - OilVoice


Posted 5 months agoPress > CNOOCChina National Offshore Oil CorporationChevron +11

Total Announces the Distribution of its Second 2018 Interim Dividend

The Board of Directors met on December 12, 2018 and declared  the distribution of a second interim dividend for the 2018 fiscal year of €0.64 per share, in accordance with the Board's decision of July 25, 2018, an amount equal to the first 2018 interim dividend and an increase of 3.2% compared to t ...

OilVoice Press - OilVoice


Posted 5 months agoPress > TotalDividend
All posts from oilvoice